What's the Timeline?
Project launch
|
Dec ’07 |
|
| Gathering of input from stakeholders | Jan-Mar ’08 | |
| Consulting contract with CSC | Apr ’08 | |
| First round table meeting | May ’08 | |
| Memorandum of understanding | Jul – Aug ’08 | |
| Choice of architect | Oct ’08 | |
| Concept design, budget received | Jan ’09 | |
| Council approval of design | Mar ‘09 | |
| Fundraising campaign | Mar ‘09 - Mar '12 | |
| Full architectural design | March '12 | |
| Construction | July '12 |